Project Timeline
-
*Timeline is approximate and actual dates may vary
September
Bond election
Fall 2018
Issue bonds; advertise for bids on construction projects
Early spring 2019
Begin construction on Career and Technical Education classrooms/labs at the main CHS campus
Summer 2019
Begin work on construction and renovation projects at Clinton Park Elementary, Lovett Elementary and Northside Elementary
Expand CHS band hall
Late 2019/early 2020
Open new CHS Career Complex classrooms/labs at Clinton High School main campus
Begin renovating old CHS Career Complex to accommodate Clinton Junior High fine arts programs and elective courses
Summer 2020
Renovate old fine arts area at CJHS into administrative offices
Convert old administrative offices at CJHS into classrooms
Fall 2020
Work is completed