Project Timeline

  • *Timeline is approximate and actual dates may vary

     

    September

    Bond election

     

    Fall 2018

    Issue bonds; advertise for bids on construction projects

     

    Early spring 2019

    Begin construction on Career and Technical Education classrooms/labs at the main CHS campus

     

    Summer 2019

    Begin work on construction and renovation projects at Clinton Park Elementary, Lovett Elementary and Northside Elementary

    Expand CHS band hall

     

    Late 2019/early 2020

    Open new CHS Career Complex classrooms/labs at Clinton High School main campus

    Begin renovating old CHS Career Complex to accommodate Clinton Junior High fine arts programs and elective courses

     

    Summer 2020

    Renovate old fine arts area at CJHS into administrative offices

    Convert old administrative offices at CJHS into classrooms

     

    Fall 2020

    Work is completed